Is a plant sited in Chonburi automatically eligible for EEC incentives?

In short

No. The three provinces are the boundary, not the qualification. On the EECO route the plant has to sit inside a designated promotional zone and the investment has to fall in one of the target clusters; on the BOI route the three provinces as a whole have already been announced as an investment promotion zone, so the baseline is the activity category and the tier. The same plot can get opposite answers depending on which route you ask under — settle the route first, then check the plot.

01The three provinces are the boundary, not the qualification

The question we hear most at site-selection stage is how much more a plot inside the EEC saves. That gets the order backwards: before you ask how much, the question that actually needs an answer is whether the plot counts at all under the route you plan to take.

The statutory scope of the EEC is only Chachoengsao, Chonburi and Rayong. Inside that scope sits a further layer, the promotional zone, and it is not an administrative area — only three classes of land can apply to be designated: industrial estates, government or PPP land, and private industrial clusters. It counts only once approved, and the list grows by announcement. So being inside the three provinces does not settle anything by itself; it only narrows the question to a boundary.

02The two routes ask different things of where you land

The EECO route lists two prerequisites: you operate inside one of the designated promotional zones, and the investment falls in one of the target clusters (medical and wellness, digital, next-generation automotive, bio-circular-green economy, services). If the plot is not on the list, this route does not hold. The BOI route is a different system: the three provinces as a whole have already been announced as an investment promotion zone, so the baseline runs on the activity category and the tier — which class of plot you land on decides only which form of location add-on you get, not whether you qualify.

Same plot, two different answers. "Not on the promotional zone list means no incentives" holds for EECO and does not hold for BOI. "Anywhere in the three provinces will do" holds for the BOI baseline and holds for neither EECO nor the location add-on. Where you hear contradictory claims, the person making them has usually not said which route they mean.

03Does Prachinburi count?

No. Prachinburi does appear in the official master development plan, but in two capacities only: the Prachinburi river and basin as an adjacent water source for EEC water allocation, and as one of the neighbouring provinces listed in cross-province statistical groupings such as health regions. Neither of those makes it part of the statutory scope. Chinese-language material folding Prachinburi into the EEC is common enough that it is worth checking before you site there.

04Three questions to settle before you pick a site

Which route am I taking — EECO or BOI? Settle this first, or everything that follows may need re-checking. Is this plot on the current list of promotional zones, and which class does it belong to? What tier is my activity category graded at? That decides whether the BOI route's location add-on is even open to you. These three questions pull on one another, and all of them turn on the announcements in force at the time of filing. Plot status, activity category and tier direction need to be verified individually against what the business actually does. See whether BOI and EEC exemption years can be added together and the order to check things in when siting.

Related

Sources

  1. Office of the Eastern Economic Corridor Policy Committee (EECO): the EEC Incentive Guide Book 2025 and the official E-leaflet — the three provinces of the statutory EEC scope, the two prerequisites for the incentives and the three classes of land that can be designated, the target clusters, and the EECO route's grant process and its four assessment dimensions. Checked 2026-08-10
  2. Board of Investment (BOI): Announcement No. 17/2565 (investment promotion measures for the Eastern Special Development Zone — the three provinces as an investment promotion zone, the applicable tiers, and the conditions and form of the capability group and location group add-ons); Announcement No. 5/2567 (replacing clause 5 — operators in a promotional zone may still apply for BOI promotion, but not for duplicate incentives on the same project). Checked 2026-08-10
  3. General note: the Eastern Special Development Zone Master Development Plan (B.E. 2566–2570) — the Prachinburi river and basin as an adjacent water source for EEC water allocation, and the neighbouring provinces listed in cross-province statistical groupings such as health regions. Checked 2026-08-10
  4. General note: this page does not determine any project's route, activity category or tier. Individual cases must be assessed by our advisers against what the business actually does and the announcements in force at the time of filing, with EECO (eeco.or.th) and Board of Investment (BOI) (boi.go.th) prevailing.
Checked against the official texts by the CTAC Thailand advisory team. We track the gazettes of the BOI, the Revenue Department, the Department of Business Development and Thai Customs every week; when an official position changes, the affected pages are updated and dated.
This page is general information based on the rules in force at the date shown. Thai BOI categories, incentive conditions and foreign-investment rules change often. Before acting on any specific project, check the latest official announcement and have a formal opinion issued on your own facts.
Check your plot against both routes

One page: whether your site is on the promotional zone list, which class it belongs to, and what it means under EECO and under BOI respectively.

中文版 · Chinese version